|
[ Home ] [ Up ]
North
Dakota Surface Water Drainage Law
Water
issues usually fall into two broad categories of "wanting to acquire
water" or "wanting to dispose of water." This page
focuses on the question of disposing of surface water from rain and snowmelt;
restated, this page addresses drainage. The discussion focuses on
North Dakota law; federal drainage law is not discussed on this page.
This page addresses just one part of the complex array of drainage issues.
This
page is for educational purposes only. Visitors are urged to seek
competent professional advice for answers to their specific questions.
Is
drainage regulated in North Dakota?
Yes.
For example, a permit is needed in some situations before landowners can
drain their land.
When
is a drainage permit needed in North Dakota?
A
permit is needed before a landowner can drain a watershed of more than
80 acres.
"Any
person, before draining a pond, slough, lake, or sheetwater, or any
series thereof, which has a watershed area comprising eighty acres [32.37
hectares] or more, shall first secure a permit to do so."
North Dakota Century Code (N.D.C.C.) 61-32-03.
For
example, a permit is needed to drain a half-acre wetland in a 100-acre
watershed. The criterion for determining whether a permit is required
is not the size of the wetland or pond, but the size of the watershed
in which the wetland is located.
A permit is required whether
the drainage involves constructing a ditch, pumping to remove the water,
extending or modifying an existing drain, or filling a wetland. North
Dakota Administrative Code (N.D.A.C.) §89-02-01-03.
- "Watershed" means the area which drains into a pond, slough,
lake, or sheetwater, or any series thereof. Also see N.D.A.C.
§89-02-01-06
- "Pond" means a well-defined land depression or basin that
holds water in normal years throughout the summer. Ponds generally go
dry only in years of below normal runoff and precipitation.
- "Series of ponds, sloughs, lakes, or sheetwater" means two
or more ponds, sloughs, lakes, or sheetwater that are hydrologically
linked naturally or artificially.
- "Sheetwater" means shallow water that floods land not normally
subject to standing water.
- "Slough" includes two types:
- a. Seasonal slough: a depression which holds water in normal years
from spring runoff until mid-July. In years of normal runoff and
precipitation, a seasonal slough is usually not tilled but can be
used for hayland or pasture. In low runoff, dry years, these areas
generally are tilled for crop production, but commonly reflood with
frequent or heavy summer or fall rains.
- b. Temporary slough: a shallow depressional area that holds water
or is waterlogged from spring runoff until early June. In years
of normal runoff and precipitation, a temporary slough is usually
tilled for crop production. In years of high runoff or heavy spring
rain, a temporary slough may not dry out until mid-July and generally
would not be tilled but may be used for hayland or pasture. A temporary
slough frequently refloods during heavy summer and fall rains.
Draining
when a permit is not needed
No
permit is needed if the watershed being drained is less than 80 acres.
Instead, North Dakota applies a common law (legal concepts that have
been defined by the courts through a series of lawsuits and decisions)
doctrine of reasonable use. The primary consideration in the reasonable
use doctrine is "what impact will the drainage have on downstream
landowners."
"Reasonable
Use"
Excerpts
from Martin
v. Weckerly, 364 N.W.2d 93 (N.D. 1985) -- a North Dakota Supreme
court decision in which the justices describe "reasonable use"
as it applies to surface water drainage.
"The
reasonable-use concept is based upon the principle that although every
landowner has the right to the use and enjoyment of his property, such
use must be reasonable so as not to cause unnecessary injury to others.
"Therefore,
drainage of surface waters complies with the reasonable-use rule if:
(a)
There is a reasonable necessity for such drainage;
(b)
If reasonable care be taken to avoid unnecessary injury to the land
receiving the burden;
(c)
If the utility or benefit accruing to the land drained reasonably outweighs
the gravity of the harm resulting to the land receiving the burden;
and
(d)
If, where practicable, it is accomplished by reasonably improving and
aiding the normal and natural system of drainage according to its reasonable
carrying capacity, or if, in the absence of a practicable natural drain,
a reasonable and feasible artificial drainage system is adopted.
"Consequently,
the objective of the reasonable-use rule is to determine whether or
not circumstances exist which will justify a court in shifting the loss
from the person harmed (the downstream landowner) to the person
causing the harm (the 'draining' landowner).
"The
reasonable necessity requirement must be considered in light
of the policy established by the reasonable-use rule to equitably balance
the developing and improving of land with any consequential harm to
other property.
"...
Weckerly conducted no investigation concerning the impact his drainage
would have on downstream landowners and that he otherwise took no significant
action to avoid unnecessary harm to Hanson's property.
"
The trial court found Weckerly's drainage was the proximate cause of
the damage to Hanson's property.
"
Weckerly asserts there was no proof that his improved drainage caused
any abnormal runoff and that any high runoff was attributable to unseasonably
high rainfall... Weckerly claims that drainage from other upstream landowners
was responsible for the bulk of the runoff, and consequently the bulk
of the drainage, to Hanson's property. We find Weckerly's argument unconvincing.
Weckerly voluntarily consented to the drainage of water onto his land
by upstream landowners. It was, or should have been, reasonably foreseeable
to Weckerly that the commingling and subsequent drainage of his surface
water with that of upstream landowners could cause harm to Hanson's
property.
"
The law should not inhibit reasonable development and improvement of
land, but neither should it allow a landowner to expel surface water
without regard to the consequences."
Also " maintaining a (natural)
drainway in its natural state does not require a drainage permit."
See Nilson v. Markestad, 353 N.W.2d 312, 314 (N.D. 1984)." Ness
v. Ward County Water Resource Dist., 1998 ND 191, 585 N.W.2d 793 http://www.court.state.nd.us/_court/opinions/980072.htm
Draining
when a permit is needed
The general rule is that a permit is required before draining a watershed
of more than 80 acres. The process of obtaining a drainage permit
is collaboratively administered by the state engineer and local water
resource management boards.
State
engineer
The
state engineer is appointted by the state water commission (N.D.C.C.
§61-03-01).
Some responsibilities of the state engineer include
- serving as secretary and chief engineer for the (state water) commission
(N.D.C.C. §61-03-01);
and
- when requested by the county commissioners of any county, cooperate
with the commissioners in the engineering work required to lay out,
establish, and construct any drain to be used by any county or counties
for the purpose of diverting floodwaters, lakes, or watercourses; aid
and assist counties in making preliminary surveys and establishing systems
of drainage (N.D.C.C. §61-03-08).
Water
Resource Management Board
In establishing water resouce
management districts, the legislature declared that the most efficient
and economical method of managing, conserving, protecting, developing,
and controlling water and related land resources is to establish water
resource districts encompassing all of the geographic area of the state,
and emphasizing hydrologic boundaries. Source: N.D.C.C.
§61-16.1-01.
Web site listing ND's water
resource management boards -- http://www.swc.state.nd.us/4DLink5/4dcgi/wrboards
Most water resource districts
are organized by county, but several are organized by watershed, e.g.,
Lower Heart, Willow Creek, and Rush River.
Selected authorities of water
resource management board
- Initiate legal action to compel an entity responsible for maintaining
and repairing a bridge or culvert to remove all dirt, rocks, weeds,
brush, shrubbery, other debris, and any artificial block which decreases
the flow of water through the bridge or culvert. N.D.C.C. §61-16.1-09(16)
- Coordinate proposals to install, modify, or construct culverts and
bridges in an effort to achieve appropriate size and maximum consistency
of road openings. The department of transportation, railroads, counties,
and townships shall cooperate with the districts in this effort. N.D.C.C.
§61-16.1-09(21)
- Encourage landowners to retain water on the land to the maximum extent
possible, and carry out the water management policy that upstream landowners
and districts that have altered the hydrologic scheme share with downstream
landowners the responsibility of managing and controlling surface waters.
N.D.C.C. §61-16.1-10(4)
- In planning any surface water project, address and consider the downstream
impacts caused by the project. A determination of whether to proceed
with the construction of a project shall be based on the following principles:
a. Reasonable necessity of
the project.
b. Reasonable care to be taken to avoid unnecessary injury by fully
considering all alternatives.
c. Whether the benefit from the project reasonably outweighs the adverse
impacts resulting from the project. N.D.C.C. §61-16.1-10(5)
- Require that appropriate easements be obtained when projects will
cause an adverse impact to lands of other landowners. N.D.C.C. §61-16.1-10(6)
Other
statutes (N.D.C.C.) relating to operations of water resource districts
§61-16.1-41.1.
Removal or placement of fill.
§61-16.1-42.
Drains along and across public roads and railroads.
§61-16.1-43.
Construction of bridges and culverts - Costs.
§61-16.1-44.
Culvert and pipe arch bids and acceptance.
§61-16.1-45.
Maintenance of drainage projects.
§61-16.1-46.
Establishing new drains in location of invalid or abandoned drain.
§61-16.1-47.
Drain kept open and in repair by water resource board.
§61-16.1-48.
Assessment of costs of cleaning and repairing drains.
§61-16.1-49.
Petition for a lateral drain - Bond of petitioners.
§61-16.1-50.
Drains having a common outlet may be consolidated.
§61-16.1-51.
Removal of obstructions to drain - Notice and hearing - Appeal -
Injunction - Definition.
Other
government entities
A frequent question is what
role do other local government entities have in managing drainage.
- County commissions --
- Township authorities --
"We have construed those
statutes as providing water resource boards with authority to direct
townships to install culverts to accommodate drains established by law,
but not in natural watercourses or to preserve a natural drainway for
surface waters. "[T]ownship boards, and not water resource districts,
have supervisory authority under N.D.C.C. § 24-03-06 to decide whether
to install a culvert beneath a township road to preserve a natural drainway
for surface waters."
"While water resource districts
have been given broad powers to control waters within their jurisdictions,
they have not been given authority to make the decision to install a
culvert under a township road in a natural watercourse. Rather, water
resource districts have the authority to direct a township to install
a culvert to accommodate a drain."
Burlington
Northern v. Benson County Water Resource District, 2000 ND 182, 618
N.W.2d 155 (http://www.court.state.nd.us/_court/opinions/990368.htm)
"Clearly, the Legislature
envisioned township and water resource district boards working together
on such decisions. The Legislature has also made it clear, however,
that a board of township supervisors, not a water resource district,
has the authority to install culverts beneath township roads when necessary
to preserve the natural drainage of surface waters." Ness
v. Ward County Water Resource Dist., 1998 ND 191, 585 N.W.2d 793
http://www.court.state.nd.us/_court/opinions/980072.htm
- State Water Commission --
- ND Department of Transportation --
- ND Game and Fish Department --
How does one apply for a drainage
permit?
A landowner can apply for a
drainage permit by completing State of North Dakota Application to
Drain form (SFN 2830). This form is available from the State
Water Commission by telephone (701-328-2752), mail (State Water Commission,
900 E. Boulevard Avenue, Bismarck, ND 58505-0850), and e-mail (cgraff@swc.state.nd.us),
or by contacting your local county Water Resource Board.
- The
permit application is submitted to the state engineer. N.D.C.C.
§61-32-03 and N.D.A.C.
§89-02-01-07.
- The state engineer then
refers the application to the water resource district or districts where
the watershed is located for the boards's consideration and approval,
but the state engineer may require that applications proposing drainage
of statewide or interdistrict significance be returned to the state
engineer for final approval. N.D.C.C. §61-32-03
and N.D.A.C. §89-02-01-08.
Drainage
with statewide or interdistrict significance --
1. Drainage which would affect property owned by the state or its political
subdivisions.
2. Drainage of sloughs, ponds, or lakes having recognized fish and wildlife
values.
3. Drainage or partial drainage of a meandered lake.
4. Drainage which would have a substantial effect on another district.
5. Drainage which would convert previously noncontributing areas (based
on twenty-five year event - four percent chance) into permanently contributing
areas.
6. For good cause, the state engineer may classify any proposed drainage
as having statewide or interdistrict significance, or the state engineer
may determine that certain proposed drainage is not of statewide or
interdistrict significance." N.D.A.C.§89-02-01-09
Criteria for granting a permit
A
permit may not be granted until an investigation discloses that the quantity
of water which will be drained will not flood or adversely affect downstream
lands. The person proposing the drain will pay for the investigation.
N.D.C.C.
§61-32-03 and N.D.A.C.
§89-02-01-09.2.
Factors
to be considered
- volume of water to be drained and its impact on the receiving wartercourse
- possible adverse effects on downstream lands
- design of drain
- impact on flooding in the watershed
- impact on waterbodies with recognized fish and wildlife values
- impact on agricultural lands
- whether (flowage?) easements are required
Observation
-- The focus of the criteria is on minimizing the adverse impact
to downstream landowners (which is consistent with the common law reasonable
use doctrine). Preservation of wetlands is not the primary statutory
criterion in determinng whether a drainage permit should be granted.
Exception -- the project's impact on waterbodies with recognized fish
and wildlife values.
If
the investigation shows that the proposed drainage will flood or adversely
affect lands of downstream landowners, the water resource board may not
issue a permit until flowage easements are obtained. The flowage easements
must be filed for record in the office of the recorder of the county or
counties in which the lands are situated. N.D.C.C.
§61-32-03
"The
obvious purpose of requiring a flowage easement is to protect downstream
landowners and insure that they receive just compensation in the event
of flooding or an adverse impact on their land." Larson
v. Wells County Water Resource Board, 385 N.W.2d 480 (N.D. 1986) http://www.court.state.nd.us/_court/opinions/11035.htm
Exception
to the general rule of when a permit is needed
A
drainage permit is
not required for the construction or maintenance of any existing or prospective
drain constructed under the supervision of a state or federal agency,
as determined by the state engineer. N.D.C.C. §61-32-03; N.D.A.C. §89-02-01-5(2).
Example
--
Maintaining
a drain
A
permit is not required to maintain a drain. N.D.A.C.
§89-02-01-05(1). "Maintenance" means removal of silt and
vegetation from a drain. Maintenance does not include deepening or widening
a drain. N.D.A.C. §89-02-01-02(7).
Modifying
a drain
A permit is required to modify
a drain. Modification includes deepening, widening, or extending a drain.
N.D.A.C.
§89-02-01-03(6).
Process of reviewing a permit
application
Upon receiving an application
for a drainage permit:
- the board will arrange a meeting;
- give notice of the meeting by publication in newspaper, and by mail
to affected landowners; state game and fish; state department of health;
state, county and township if the drain will cross a public roadway;
state engineer; and others who asked to be notified;
- applicant must submit all documents intended to be used at the meeting
at least 14 days before the meeting;
- the board will allow relevant oral and written evidence to be presented
at the meeting;
- the meeting must be recorded;
- board must make decision on application within 60 days of receiving
the application (N.D.A.C.
§89-02-01-09.3)
- if application is approved, all documents will be transferred to the
state engineer; notice will be sent to all interested person with the
board's rationale; and the board must specify the location and size
of the areas to be drained;
- if application is denied, board must provide its rationale to the
applicant; this decision can be appealed to the district court. (N.D.A.C.
§89-02-01-09.1)
In reviewing an application
of a statewide or interdistrict significance
- the state engineer will consider the information received from the
board, information the engineer assembles, and information the engineer
requests from other sources (N.D.A.C.
§89-02-01-09.4)
- the state engineer will provide information about its decision to
interested persons (N.D.A.C. §89-02-01-09.5)
- Within 30 days after the decision, a hearing can be requested (N.D.A.C.
§89-02-01-09.6); hearing
procedure is set forth in N.D.A.C. §§89-02-01-09.7
to -09.10
Drainage permits can be modified
by the government to protect public health, safety and welfare. (N.D.A.C.
§§89-02-01-09.11)
Construction must begin within
two years of receiving the permit (unless extended for one more year).
Construction must proceed with good faith efforts and satisfactory
progress. (N.D.A.C. §§89-02-01-09.11
and -09.12)
Emergency drainage
The
state engineer may adopt rules for temporary permits for emergency drainage.
N.D.C.C.
§61-32-03
An emergency ... is a situation which
if not addressed immediately will cause significant damage to persons
or property which would not occur under normal circumstances. An emergency
may exist as a result of an extremely wet cycle. However, damages
caused by deliberate acts of any individual do not constitute an emergency
... unless the damage can be alleviated without harm to other persons
or property. (N.D.A.C.§89-02-05.1-04)
- Application for an emergency drain must be sent simultaneously to
the board and the state engineer.
- Application will be reviewed for completeness by the board and the
state engineer.
- Board and state engineer will make a preliminary determination as
to the existence of an emergency.
- As soon as possible, a conference call or an onsite meeting among
the board, the state engineer, and other affected parties, as determined
by the state engineer, must be held. The applicant or any other affected
party may make a statement concerning the emergency drainage application
during the conference call or onsite meeting.
- Any conference call or onsite meeting must be electronically recorded.
- During the call or meeting, but after all parties have been given
an opportunity to present their views, the board shall make a recommendation
to the state engineer whether or not the license should be granted. (N.D.A.C.
§89-02-05.1-06)
- After the conference call or onsite meeting, the state engineer shall
consider the written information received, the matters discussed during
the conference call or onsite meeting, and the recommendation of the
board, and (based upon this information) decide whether the emergency
license should be granted.
- If the license is granted, the state engineer may impose any condition
the state engineer deems necessary to protect public or private interests;
a condition may include [requiring a bond].
- The license must be limited to no more than six months. (N.D.A.C.
§89-02-05.1-07)
A license [for an emergency drain] has a duration of not more than six
months unless extended. (N.D.A.C. §89-02-05.1-03)
- A
license for an emergency drain does not relieve the applicant of liability
for damages resulting from any activity conducted pursuant to the license.
(N.D.A.C. §89-02-05.1-10)
- If the drain is to be permanent, the applicant shall
submit a drainage permit application to the state engineer. If the application
is submitted no later than 30 days prior to the date the emergency license
expires, the term of the emergency license is extended until final action
on the drainage permit application has been taken, unless the state
engineer determines that the drain should be closed to prevent damage
to public or private interests. (N.D.A.C.
§89-02-05.1-08)
- If an application
for a permanent drainage permit is not submitted 30 days prior to the
date the emergency license expires, the applicant shall immediately
make preparations to close the drain unless the applicant has applied
in writing for an extension from the state engineer and that extension
has been granted. Preparations must include entering by other individuals,
obtaining any permission necessary from other landowners, and obtaining
any permission or authorizations necessary. The drain must be closed
on or before the license expires. The applicant shall keep the board
and the state engineer informed of the applicant’s progress in
closing the drain. (N.D.A.C. §89-02-05.1-09)
Concerns/complaints
about drainage
Complaints about unauthorized
drainage are filed with the local water resource management board.
- Only a landowner who is adversely impacted can file a complaint about
an unauthorized drain constructed before January 1, 1975, but any person
may file a complaint about an unauthorized drain constructed after January
1, 1975. (N.D.C.C.
§61-32-07)
- Upon receipt of a complaint, the water resource board shall promptly
investigate and make a determination of the facts (N.D.C.C. §61-32-07)
- The board shall make the decision within a reasonable time, not to
exceed 120 days, after receiving the complaint. (N.D.C.C. §61-32-08)
- If the board fails to investigate and make a determination concerning
the complaint, the person filing the complaint may file it with the
state engineer. (N.D.C.C. §61-32-08)
Board Action
- If, after the first complaint, the board's opinion is that the complaint
is frivolous, the board may assess the costs of the frivolous complaint
against the complainant. (N.D.C.C.
§61-32-07)
- If the board determines that the drain is unauthorized, the board
shall notify the landowner by registered mail; a copy of the notice
must also be sent to the tenant, if known.
- The notice must specify the nature and extent of the noncompliance,
and state that if the drain is not closed within a reasonable time (as
the board determines, but not less than 15 days), the board will have
the drain closed and assess the cost of the closing against the property
of the responsible landowner(s).
- The affected landowner has 15 days from the date the notice is mailed
to demand, in writing, a hearing on the matter. (N.D.C.C. §61-32-07)
A. Demand hearing before water
resource management board
Upon receipt of a demand for
a hearing, the board shall set a hearing date within 15 days from the
date the demand is received. (N.D.C.C.
§61-32-07)
- In the event of an emergency, the board may immediately apply to the
appropriate district court for an injunction prohibiting the landowner
or tenant from constructing or maintaining the drain, and ordering the
illegal drain be closed. (N.D.C.C. §61-32-07)
- The board shall notify all parties of its decision by certified mail.
(N.D.C.C. §61-32-08)
B. Appeal to district court
A person aggrieved by action
of the board may appeal the decision of the board to the district court.
A hearing as provided for in this section is not a prerequisite to an
appeal. (N.D.C.C. §61-32-07)
A court case that may be
of interest -- Graber
v. Logan County Water Resource Board, 1999 ND 168, 598 N.W.2d 846
http://www.court.state.nd.us/_court/opinions/990029.htm
This case involved several
appeals and provides an example of the appeals process.
Also, "the hearings
in this case focused mainly on whether the drainage ditch on Graber's
property was dug before or after 1957. The law in effect at the time
a drain is constructed controls, ... and the ... statute ... requiring
drainage permits, was not enacted until 1957."
C. Appeal to state engineer
The board's decision may be
appealed to the state engineer by any aggrieved party. (N.D.C.C. §61-32-08
)
- The appeal to the state engineer must be made within 30 days from
the date notice of the board's decision has been received. The appeal
must be made by submitting a written notice to the state engineer and
set forth the reason why the board's decision is erroneous. (N.D.C.C.
§61-32-08)
- The appealing party shall also submit copies of the written appeal
notice to the board and to the nonappealing party. (N.D.C.C. §61-32-08)
- Upon receipt of this notice the board, if it has ordered a drain to
be closed, is relieved of its obligation to close the drain.(N.D.C.C.
§61-32-08)
- The state engineer shall handle the appeal by conducting an independent
investigation and making an independent determination. The state engineer
may enter property affected by the complaint for the purpose of investigating
the complaint. (N.D.C.C. §61-32-08)
- The state engineer shall investigate and make a determination, either
by action against the board, or by personally conducting the investigation
and personally making the determination. N.D.C.C. §61-32-08
- If the state engineer determines the drain is illegal, the state engineer
shall take one of three actions:
1. Notify the landowner by registered mail at the landowner's post-office
address of record;
2. Return the matter to the jurisdiction of the board along with the
investigation report; or
3. Forward the drainage complaint and investigation report to the state's
attorney.
(N.D.C.C. §61-32-08)
1. If the state engineer
decides to notify the landowner, the notice must specify the nature and
extent of the noncompliance and state that if the drain is not closed
within such reasonable time as the state engineer shall determine (but
not less than thirty days), the state engineer shall close the drain and
assess the cost against the property of the responsible landowner(s).
(N.D.C.C. §61-32-08)
-
Demand hearing before state
engineer
The affected landowner may,
within 15 days of the date the notice is mailed, demand, in writing,
a hearing on the matter. Upon receipt of the demand, the state engineer
shall set a hearing date within 15 days from the date the demand is
received. (N.D.C.C.
§61-32-08)
Any person aggrieved by action
of the state engineer may appeal to the district court. A hearing by
the state engineer is required before such an appeal. (N.D.C.C. §61-32-08)
2. If the state engineer decides
to return the matter to the board, a complete copy of the investigation
report shall be forwarded to the board and it shall include the nature
and extent of the noncompliance. Upon having the matter returned, the
board shall carry out the state engineer's decision (N.D.C.C. §61-32-08)
3. If the state engineer decides
to forward the drainage complaint to the state's attorney, a complete
copy of the investigation report must also be forwarded and include the
nature and extent of the noncompliance. The state's attorney shall prosecute
the complaint. (N.D C.C. §61-32-08)
Court action
In addition to the penalty imposed
by the court in the event of conviction under this statute, the court
shall order the drain closed or filled within such reasonable time period
as the court determines, but not less than 30 days. If the drain is not
closed within the time prescribed by the court, the court shall procure
the closing of the drain and assess the cost against the property responsible
landowner(s). (N.D.C.C.
§61-32-08)
"The authority granted
in this section may only be exercised for drainage constructed after January
1, 1987." N.D.C.C. §61-32-08
Penalty
Any
person draining without first securing a permit to do so ... is liable
for all damage sustained by any person caused by the draining, and is
guilty of an infraction. (N.D.C.C. §61-32-03)
Filling
a wetland
Another
way to eliminate a wetland is to fill it, but this also is regulated;
that is, the Federal Clean Water act prohibits the discharge of material/fill
into a waterbody without a permit. The federal law also allows states
to administer this permitting process. North Dakota has a statute,
that has not yet taken affect, which states
"...no
person may discharge dredged or fill material into waters of the state
unless that person has a permit from the state engineer. No person may
discharge dredged or fill material in violation of a permit."
N.D.C.C. §61-38-05.
This
potential law can be found in N.D.C.C.
61-38.
North
Dakota also has a regulation that requries a permit before filling a wetland.
(N.D.A.C. §89-02-01-03(7))
Additional
resources
Web
site with additional information about North Dakota drainage permits
http://www.swc.state.nd.us/Permits/DrainPermits.html
North
Dakota Statutes
North
Dakota Regulations
last updated -- November 25, 2003 by David Saxowsky,
NDSU |